26.
Commissioners Court - Regular Session
- Meeting Date:
- 08/31/2021
- Title:
- CR 375 Temporary Closure
- Submitted For:
- Terron Evertson
- Submitted By:
- Vicky Edwards, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action regarding the temporary closing of CR 375 for road work to replace cross culverts.
Background
The proposed roadway closure and detour of CR 375, in three locations, is necessary in order to replace cross drainage culverts. The nearest addresses of the closures are 440 CR 375, 640 CR 375, and 930 CR375. The closure will start on or around 9/17/2021 and continue until December 2021.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 08/26/2021 09:25 AM |
- Form Started By:
- Vicky Edwards
- Started On:
- 08/19/2021 10:26 AM
- Final Approval Date:
- 08/26/2021