50.
Commissioners Court - Regular Session
- Meeting Date:
- 09/21/2021
- Title:
- 1907-333 O'Connor Traffic Signals Change Order No. 4
- Submitted By:
- Mayra Ramos, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $37,546.50 for 1907-333 O'Connor Traffic Signals (Champion Infrastructure) P:329 Funding Source: Road Bond.
Background
This Change Order provides for the balancing of overruns to various Contract quantities on the project as a result of addressing field conditions not accounted for in the original plans. The overruns of quantities include conduit, wire and cable, due to the relocation of the signal controller at Liberty Walk. Relocation of the signal controller foundation was added by Change Order Number 3.
Item 531-6003 Concrete Sidewalk (6”) quantities were increased at various locations due to the cross slopes of the existing sidewalk and requirements to meet ADA regulations.
Item 618-6046 Conduit (PVC)(Sch 80)(2”) quantities were increased due to the relocation of the signal controller at Liberty Walk and new locations for ground boxes at various intersections, due to conflicts with existing utilities.
Items 620 Electrical Conductor quantities for wiring were increased due to the relocation of the signal controller at Liberty Walk and new locations for signal poles and ground boxes at various intersections, due to conflicts with existing utilities.
Items 6002 and WC9015 Coaxial Cable quantities were increased due to the relocation of the signal controller at Liberty Walk and new locations for signal poles and ground boxes at various intersections, due to conflicts with existing utilities.
This Change Order results in an increase of $37,546.50 to the Contract amount, for an adjusted Contract total of $1,022,105.38. The original Contract amount was $853,503.50. Because of this Change Order, $168,511.88 has been added to the Contract, resulting in a 19.74% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
Item 531-6003 Concrete Sidewalk (6”) quantities were increased at various locations due to the cross slopes of the existing sidewalk and requirements to meet ADA regulations.
Item 618-6046 Conduit (PVC)(Sch 80)(2”) quantities were increased due to the relocation of the signal controller at Liberty Walk and new locations for ground boxes at various intersections, due to conflicts with existing utilities.
Items 620 Electrical Conductor quantities for wiring were increased due to the relocation of the signal controller at Liberty Walk and new locations for signal poles and ground boxes at various intersections, due to conflicts with existing utilities.
Items 6002 and WC9015 Coaxial Cable quantities were increased due to the relocation of the signal controller at Liberty Walk and new locations for signal poles and ground boxes at various intersections, due to conflicts with existing utilities.
This Change Order results in an increase of $37,546.50 to the Contract amount, for an adjusted Contract total of $1,022,105.38. The original Contract amount was $853,503.50. Because of this Change Order, $168,511.88 has been added to the Contract, resulting in a 19.74% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/16/2021 08:42 AM |
- Form Started By:
- mayra.ramos
- Started On:
- 09/13/2021 01:58 PM
- Final Approval Date:
- 09/16/2021