41.
Commissioners Court - Regular Session
- Meeting Date:
- 12/14/2021
- Title:
- Approve Amendment #1 to Contract for CMAR for Expo Center Various Improvements Project between Chasco Constructors Ltd, LLC
- Submitted For:
- Joy Simonton
- Submitted By:
- Johnny Grimaldo, Purchasing
- Department:
- Purchasing
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action on approving amendment No 1 to contract for Construction Manager At Risk (CMAR) for Expo Center Various Improvements Project between Chasco Constructors Ltd, LLC reducing the original CMAR’s Fee from $509,850.00 to $305,496.00, and authorizing execution of the agreement. P562
Background
Due to negotiations following execution of the contract, Chasco Constructors, Ltd, LLC and Williamson County were able to reduce the original CMAR’s Fee from $509,850.00 to $305,496.00, and it has become necessary to amend Subsection 5.1.1 of the contract which was approved by the commissioners’ court on 06.08.2021, item 44. The Construction Manager at Risk fee shall be a fixed sum of $305,496.00 which is comprised of a CMAR’s Fee of $86,491.00 for Package1 improvements and a CMAR’s Fee for $219,005.00 for bid package 2 improvements. The Point of Contact is Angel Gomez.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 12/09/2021 09:40 AM |
- Form Started By:
- Johnny Grimaldo
- Started On:
- 12/08/2021 02:29 PM
- Final Approval Date:
- 12/09/2021