- 22IFB39 - CR 111 Westinghouse Rd - Change Order#2 (Storm Drainage Revisions)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $7,553.84 for Project 22IFB39 CR 111 Westinghouse Rd. (Capital Excavation) P: 292 Funding Source: Road Bond.
Background
This Change Order adds pay items to revise the size of 6 curb inlets and 1 junction box on the project. New items are being added to change 6 curb inlets from 3 feet wide to 4 feet wide inlets and a junction box from 4’ x 4’ to a 5’ x 5’ dimension box. The drainage structures need to be larger than those originally shown in the plans, to accommodate the size of pipe used in the drainage system. This Change Order will compensate the contractor for the difference in the cost of the drainage structures.
The following new items will be added by this Change Order.
This Change Order results in a net increase of $7,553.84 to the Contract amount, for an adjusted Contract total of $21,265,250.72. The original Contract amount was $21,024,332.88. As a result of this and all Change Orders to-date, $240,917.84 has been added to the Contract, resulting in a 1.15% net increase in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.
The following new items will be added by this Change Order.
| ITEM | DESCRIPTION | QTY | UNIT |
| 465-6009 | JCTBOX (COMPL) (PJB) (5FTX5FT) | 1 | EA |
| 465-6020 | INLET (COMPL) (PCO) (4FT) (BOTH) | 6 | EA |
This Change Order results in a net increase of $7,553.84 to the Contract amount, for an adjusted Contract total of $21,265,250.72. The original Contract amount was $21,024,332.88. As a result of this and all Change Orders to-date, $240,917.84 has been added to the Contract, resulting in a 1.15% net increase in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
- 22IFB39 - CR 111 Westinghouse Rd - CO#2(Storm Drainage Revisions)
- 22IFB - CR 111 Westinghouse Rd - CO#2(Storm Drainage Revisions)
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 04/28/2022 08:34 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 04/26/2022 10:45 AM
- Final Approval Date:
- 04/28/2022