75.
Commissioners Court - Regular Session
Meeting Date:
09/13/2022
Title:
22IFB68 Wyoming Springs Intersection Improvements at Smyers Lane - Change Order #2 (Balancing)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of ($41,610.00) for Project 22IFB68 Wyoming Springs Intersection Improvements at Smyers Lane (MA Smith Contracting) P: 339 Funding Source: Road Bond.

Background

This Change Order provides the final balancing for the overrun/underrun of contract quantities on the project, as a result of addressing field conditions not accounted for in the original plans. 

This Change Order results in a net decrease of $41,610.00 to the Contract amount, for an adjusted Contract total of $314,282.50. The original Contract amount was $355,892.50. As a result of this and all Change Orders to-date, $41,610.00 has been removed from the Contract, resulting in a 11.69% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 09/01/2022 09:10 AM
Form Started By:
Julissa Romero
Started On:
08/25/2022 10:46 AM
Final Approval Date:
09/01/2022