77.
Commissioners Court - Regular Session
- Meeting Date:
- 09/13/2022
- Title:
- 22IFB57 CR 401 Reconstruction Change Order #1 (US 79 Pavement)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $13,315.52 for Project 22IFB57 CR 401 Reconstruction (James Construction) P: 390c Funding Source: Road Bond.
Background
This Change Order revises the US 79 pavement section to meet TxDOT requirements. Adjustments to the signal phasing/timing for the new intersection at proposed US 79 and CR 401 are also included to meet TxDOT requirements.
The following new items will be added by this Change Order.
This Change Order results in an increase of $13,315.52 to the Contract amount, for an adjusted Contract total of $12,686,516.46. The original Contract amount was $12,673,200.94. As a result of this and all Change Orders to-date, $13,315.52 has been added to the Contract, resulting in a 0.11% net increase to the overall Contract cost. As a result of this Change Order, zero (0) days will be added to the contract.
The following new items will be added by this Change Order.
| ITEM | DESCRIPTION | QUANTITY | UNIT |
| 3076-6050 | D-GR HMA TY-D SAC-B PG76-22 | 210.00 | TON |
| 3076-6066 | TACK COAT | 149.00 | GAL |
| 3085-6001 | UNDERSEAL COURSE | 491.00 | GAL |
| 999-WC02 | SUBCONTRACTOR MARK-UP (5%) | 1,988.56 | DOL |
This Change Order results in an increase of $13,315.52 to the Contract amount, for an adjusted Contract total of $12,686,516.46. The original Contract amount was $12,673,200.94. As a result of this and all Change Orders to-date, $13,315.52 has been added to the Contract, resulting in a 0.11% net increase to the overall Contract cost. As a result of this Change Order, zero (0) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
- 22IFB57 - CR 401 Reconstruction CO#1
- Judge Gravell Conflict of Interest
- 22IFB57 - CR 401 Reconstruction CO#1
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/08/2022 10:32 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 08/25/2022 10:59 AM
- Final Approval Date:
- 09/08/2022