30.
Commissioners Court - Regular Session
- Meeting Date:
- 10/25/2022
- Title:
- Final plat for Santa Rita Ranch Phase 1 Section 23 subdivision – Pct 2
- Submitted For:
- Terron Evertson
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Division:
- Road & Bridge
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the final plat for Santa Rita Ranch Phase 1 Section 23 subdivision being signed and certified by the Engineer and Surveyor on October 11, 2022 – Precinct 2.
Background
This is the next section of the Santa Rita Ranch Phase 1 development. It consists of 19 single family lots, 3 open space/drainage lots and 881 feet of new public roads. Roadway and drainage construction are not yet complete but a financial security in the amount of $848,983.25 has been posted with the County to cover the cost of the remaining construction. Pursuant to the Commissioners Court action taken September 10, 2019, the County Engineer has previously approved this final plat on September 2, 2022, in order to meet the review timelines set forth in House Bill 3167. Since the previous approval, the developer desired to make minor changes to the ownership information on the final plat. Upon approval, this final plat will take the place of the final plat that was previously approved by the County Engineer on September 2, 2022. The previously approved final plat has not been and shall not be submitted to the County Clerk’s Office for recordation.
Timeline
2022-07-19 – initial submittal of final plat
2022-07-19 – receipt of financial security for the remaining construction
2022-08-18 – 1st review complete with comments
2022-08-19 – 2nd submittal of final plat with signatures
2022-08-25 – 2nd review complete with comments clear
2022-09-02 – County Engineer approval letter sent
2022-10-17 – receipt of updated final plat with minor changes and signatures
2022-10-20 – review complete with comments clear
2022-10-20 – final plat placed on the October 25, 2022 Commissioners Court agenda for consideration
Timeline
2022-07-19 – initial submittal of final plat
2022-07-19 – receipt of financial security for the remaining construction
2022-08-18 – 1st review complete with comments
2022-08-19 – 2nd submittal of final plat with signatures
2022-08-25 – 2nd review complete with comments clear
2022-09-02 – County Engineer approval letter sent
2022-10-17 – receipt of updated final plat with minor changes and signatures
2022-10-20 – review complete with comments clear
2022-10-20 – final plat placed on the October 25, 2022 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 10/20/2022 12:04 PM |
- Form Started By:
- Adam Boatright
- Started On:
- 10/20/2022 11:57 AM
- Final Approval Date:
- 10/20/2022