41.
Commissioners Court - Regular Session
- Meeting Date:
- 01/10/2023
- Title:
- Chasco 22IFB48 Garden Park CO 1
- Submitted For:
- Robert Daigh
- Submitted By:
- Vicky Edwards, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No 1 to contract number 22IFB48 in the amount of -$108,148.48 for Garden Park Subdivision Roadway and Drainage. Funding source: P491.
Background
This Change Order is a balancing Change Order. All work has been completed. Original contract amount was $619,119.00; with the addition of this change order for -$108,148.48, the final contract amount will be $510,970.52.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 12/29/2022 11:55 AM |
- Form Started By:
- Vicky Edwards
- Started On:
- 12/28/2022 02:42 PM
- Final Approval Date:
- 12/29/2022