40.
Commissioners Court - Regular Session
- Meeting Date:
- 01/24/2023
- Title:
- 22IFB126 - Samsung Highway (Previously Future County Rd) (CR 404 to FM 973) Change Order #1
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $41,260.00 for Project 22IFB126 - Samsung Highway (Previously Future County Rd) (CR 404 to FM 973) (Chasco Construction) P: 619 Funding Source: Road Bond.
Background
This Change Order adds two new pay items to the Contract for installing a 4’ X 2’ box culvert (Culvert EE) and related wingwalls/headwalls. The work was shown in the plans but was not included in the bid tab.
This Change Order also removes the SET (TY 1) (S=5FT) (HW=3FT) (6:1) (C) item from the Contract. The work was removed from the plans, but the items were left in the bid tab.
These changes are due to the plan revisions made prior to bidding when the tie-in to FM 973 was eliminated from this Contract.
Multiple items will be added by this Change Order. Please see attached Change Order.
This Change Order results in a net increase of $41,260.00 to the Contract amount, for an adjusted Contract total of $11,331,189.00. The original Contract amount was $11,289,929.00. As a result of this and all Change Orders to-date, $41,260.00 has been added to the Contract, resulting in an 0.37% net increase in the overall Contract cost.
This Change Order also removes the SET (TY 1) (S=5FT) (HW=3FT) (6:1) (C) item from the Contract. The work was removed from the plans, but the items were left in the bid tab.
These changes are due to the plan revisions made prior to bidding when the tie-in to FM 973 was eliminated from this Contract.
Multiple items will be added by this Change Order. Please see attached Change Order.
This Change Order results in a net increase of $41,260.00 to the Contract amount, for an adjusted Contract total of $11,331,189.00. The original Contract amount was $11,289,929.00. As a result of this and all Change Orders to-date, $41,260.00 has been added to the Contract, resulting in an 0.37% net increase in the overall Contract cost.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 01/19/2023 08:21 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 01/11/2023 02:42 PM
- Final Approval Date:
- 01/19/2023