Commissioners Court - Regular Session
- Meeting Date:
- 07/18/2023
- Title:
- 22IFB110 Southwest Bypass Extension - Change Order #1 (Additional Work)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $3,440.89 for Project 22IFB110 Southwest Bypass Extension (Joe Bland Construction) P: 352 Funding Source: Road Bond.
Background
This Change Order compensates the Contractor for additional work related to several different changes made after the final plans were finalized.
This Change Order results in a net increase of $3,440.89 to the Contract amount, for an adjusted Contract total of $4,291,983.89. The original Contract amount was $4,288,543.00. As a result of this and all Change Orders to-date, $3,440.89 has been added to the Contract, resulting in a .08% net increase in the overall Contract cost. As a result of this Change Order, thirty seven (37) days will be added to the contract.
- The ditch line along the north side of Wolf Ranch was adjusted to avoid conflict with the City of Georgetown water line and proposed valve.
- Per TCEQ’s request, cave gates were installed at Lobo’s Lair and Rattlesnake Cave in lieu of the proposed chain link fence around the perimeter.
- The alignment of the Shared Use Path under the bridge was revised to better accommodate the future City Park and adjacent development.
- A concrete driveway was placed to tie into existing concrete at the Wolf Ranch Apartments, instead of placing asphalt.
- Due to the high rate of speed and the amount of traffic on SH 29, concrete barriers were installed for additional safety measures to protect the workers while constructing the eastbound widening on SH 29 at Southwest Bypass.
This Change Order results in a net increase of $3,440.89 to the Contract amount, for an adjusted Contract total of $4,291,983.89. The original Contract amount was $4,288,543.00. As a result of this and all Change Orders to-date, $3,440.89 has been added to the Contract, resulting in a .08% net increase in the overall Contract cost. As a result of this Change Order, thirty seven (37) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 07/13/2023 09:23 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 07/12/2023 12:25 PM
- Final Approval Date:
- 07/13/2023