22IFB139 FM 3349 at US 79 - Change Order #6 (Jonah Water Line Upsize)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 6 in the amount of $130,053.00 for Project 22IFB139 FM 3349 at US 79 (James Construction Group) P: 332 Funding Source: Road Bond.
 

Background

This Change Order compensates the contractor for upsizing 562 LF of PVC pipe from 12 inches to 16 inches for the Jonah Water Special Utility District due to increased demand. This change is being made at Jonah’s request and will be 100% funded by the Jonah Water Special Utility District. Multiple items will be added by this Change Order. Please see attached Change Order.

This Change Order results in a net increase of $130,053.00 to the Contract amount, for an adjusted Contract total of $82,795,981.18. The original Contract amount was $81,941,038.13.  As a result of this and all Change Orders to-date, $854,943.05 has been added to the Contract, resulting in an 1.04% net increase in the Contract cost.  No additional days will be added to or deducted from the Contract as a result of this Change Order. 

 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 10/12/2023 08:28 AM
Form Started By:
Julissa Romero
Started On:
10/11/2023 09:10 AM
Final Approval Date:
10/12/2023