Commissioners Court - Regular Session
- Meeting Date:
- 01/30/2024
- Title:
- CTTC Generator (445P/445A/2.1) – Change Order 2
- Submitted For:
- Dale Butler
- Submitted By:
- Wendy Danzo, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on accepting a report from Austin Montgomery d/b/a The Roof Co. Waco, LLC, Change Order No. 2 for the CTTC Generator (ARPA 445P/445A/2.1)) requiring a time extension for an addition 90 days toward substantial completion for a new date of April 1, 2024. Final Completion shall be on or before May 1, 2024. Funding Source is 445P/445A/2.1).
Background
This change order is for a time extension only of 90 days due to supply delays. Substantial Completion shall be April 1, 2024 with Final Completion being on or before May 1, 2024. Department point of contact is Angel Gomez, Sr. Project Manager, Facilities Management. On March 6, 2018, the Williamson County Commissioners Court approved Williamson County Facilities Director, Dale Butler, with authority to approve change orders under Local Government Code Sec. 262.031, in relation to Williamson County construction and facilities projects. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court. Funding for this project will be 445P/445A/2.1.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Hal Hawes | Hal Hawes | 01/25/2024 12:11 PM |
| County Judge Exec Asst. | Becky Pruitt | 01/25/2024 12:43 PM |
- Form Started By:
- wendy.danzoy
- Started On:
- 01/25/2024 11:27 AM
- Final Approval Date:
- 01/25/2024