43.
Commissioners Court - Regular Session
Meeting Date:
04/16/2024
Title:
22IFB139 FM 3349 at US 79 - Change Order #12 (Jonah UPRR US79 Bore)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 12 in the amount of $64,791.00 for Project 22IFB139 FM3349 US79 (James Construction) P: 332 Funding Source: Road Bond.

Background

This Change Order provides compensation to the Contractor for modifying the encasement length and elevation of the Jonah water line bored under US 79 and UPRR. These changes were necessary to clear a conflict with an existing gas line and to provide encasement for the water line through the UPRR ROW. In addition, this Change Order compensates the Contractor for abandoning (capping and grouting) the existing 2" Jonah water line located within UPRR ROW on the South side of US 79. Please see attached Change Order for additional details.

This Change Order results in a net increase of $64,791.00 to the Contract amount, for an adjusted Contract total of $83,820,243.45. The original Contract amount was $81,941,038.13.  As a result of this and all Change Orders to-date, $1,879,205.32 has been added to the Contract, resulting in an 2.29% net increase in the Contract cost.  No additional days will be added to or deducted from the Contract as a result of this Change Order. 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 04/11/2024 11:21 AM
Form Started By:
Julissa Romero
Started On:
04/01/2024 08:32 AM
Final Approval Date:
04/11/2024