52.
Commissioners Court - Regular Session
Meeting Date:
05/07/2024
Title:
22IFB138 - CR 366 Change Order #3 (Safety Improvements)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 3 in the amount of $71, 050.63 for Project 22IFB138 CR 366 (James Construction) P: 296 Funding Source: Road Bond.

Background

This Change Order compensates the Contractor for various items paid under Force Account to address additional safety improvements, repairs to existing CR 366, and potholing to locate existing fiber optic lines. This Change Order also compensates the Contractor for widening a driveway on CR 369, replacing unsuitable material on CR 366, installing an underdrain pipe, removing Oncor poles on CR 366 and FM 397, and paying off duty police officers needed for traffic control. Please see attached Change Order for additional details.

This Change Order results in a net increase of $71,050.63 to the Contract amount, for an adjusted Contract total of $17,858,891.39. The original Contract amount was $17,694,262.46. As a result of this and all Change Orders to-date, $164,628.93 has been added to the Contract, resulting in an 0.93% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 05/02/2024 09:08 AM
Form Started By:
Julissa Romero
Started On:
04/24/2024 09:49 AM
Final Approval Date:
05/02/2024