40.
Commissioners Court - Regular Session
- Meeting Date:
- 05/07/2024
- Title:
- Approval of the Guaranteed Maximum Price (GMP) No.2 with #22RFP148 Construction Manager at Risk (CMAR) for Williamson County New Headquarters Building to Chasco Contractors, Ltd. L.L.P. Inc. for Facilities Maintenance
- Submitted For:
- Joy Simonton
- Submitted By:
- Stacian Williams, Purchasing
- Department:
- Purchasing
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action on approving the Guaranteed Maximum Price Proposal (GMP) No.2 early release – Piers, with awarded RFP #22RFP148 Construction Manager at Risk (CMAR) New Headquarters Building, Chasco Contractors, Ltd. L.L.P. Inc, in the not-to-exceed amount $3,482,825.00 and authorize the execution of the GMP No. 2 between Williamson County and Chasco Constructors, Ltd. LPP. Inc. The funding source is P577.
Background
The Guaranteed Maximum Price (GMP) No.2 – Piers is in relation to the construction of Williamson County Headquarters through RFP #22RFP148 which was awarded on 12.13.2022 with agenda item #35, to perform the work approved on the above-mentioned project. This project is done in phases and therefore multiple GMPs are requested at different times. The funding source is P577, and the point(s) of contact are Dale Butler and Trenton Jacobs.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
- Guaranteed Maximum Price (GMP) No.2
- Form 1295 - Chasco Contractors, Ltd. L.L.P. Inc
- Guaranteed Maximum Price (GMP) No.2
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 05/02/2024 08:33 AM |
- Form Started By:
- stacian.williams
- Started On:
- 04/30/2024 04:39 PM
- Final Approval Date:
- 05/02/2024