Commissioners Court - Regular Session
- Meeting Date:
- 05/07/2024
- Title:
- 22IFB110 Southwest Bypass Extension - Change Order #5 (Final Balancing)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 5 in the amount of $12,600.00 for Project 22IFB110 SW Bypass Extension (Joe Bland Construction) P: 352 Funding Source: Road Bond.
Background
This Change Order provides the final balancing for the overruns/underruns of contract quantities on the roadway portion of the Southwest Bypass Extension project that are a result of addressing field conditions not accounted for in the original plans.
This Change Order results in a net increase of $12,600.00 to the Contract amount, for an adjusted Contract total of $3,914,316.23. The original Contract amount was $4,288,543.00. As a result of this and all Change Orders to-date, $374,226.77 has been deducted from the Contract, resulting in an 8.73% net decrease in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
This Change Order results in a net increase of $12,600.00 to the Contract amount, for an adjusted Contract total of $3,914,316.23. The original Contract amount was $4,288,543.00. As a result of this and all Change Orders to-date, $374,226.77 has been deducted from the Contract, resulting in an 8.73% net decrease in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 05/02/2024 09:09 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 05/01/2024 10:16 AM
- Final Approval Date:
- 05/02/2024