Skip to main content

AgendaQuick™

View Agenda Item

52.
Commissioners Court - Regular Session
Meeting Date:
07/16/2024
Title:
22IFB139 FM3349 at US79 - Change Order #15 (Lone Star HMAC Low Production)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 15 in the amount of $24,513.18 for Project 22IFB139 FM3349 at US79 (James Construction) P: 332 Funding Source: Road Bond.

Background

This Change Order provides compensation to the Contractor for additional construction surveying, traffic control management, and increased costs resulting from low asphalt placement production rates due to different site conditions at driveway No. 5 of the northbound frontage road. After the project was bid, a new development tied the driveway to the existing FM 3349. In order to keep the driveway operational at all times, the connection to the newly built NBFR required multiple traffic switches, re-staking to match existing conditions, and the usage of full depth HMAC. Please see attached Change Order for additional details.

This Change Order results in a net increase of $24,513.18 to the Contract amount, for an adjusted Contract total of $84,028,306.50. The original Contract amount was $81,941,038.13.  As a result of this and all Change Orders to-date, $2,087,268.37 has been added to the Contract, resulting in an 2.55% net increase in the Contract cost.  No additional days will be added to or deducted from the Contract as a result of this Change Order. 
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 07/11/2024 10:27 AM
Form Started By:
Julissa Romero
Started On:
07/10/2024 11:23 AM
Final Approval Date:
07/11/2024