Discuss, consider and take appropriate action on Change Order No 2 to contract number 24IFB29 in the amount of -$30,975.67 for CR 283 Foam Asphalt Stabilization Roadway and Drainage Improvements. Funding source: 01.0200.0210.003599.
Background
This Change Order No 2 is a balancing Change Order. All work has been completed and punch list items appropriately resolved. The original contract amount was $1,295,908.25. With the addition of Change Order No 1 in the amount of $11,191.68 and this Change Order No 2 for -$30,975.67, the final contract amount will be $1,276,124.26.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 11/05/2024 11:32 AM |
- Form Started By:
- Vicky Edwards
- Started On:
- 11/04/2024 08:10 AM
- Final Approval Date:
- 11/05/2024