Skip to main content

AgendaQuick™

View Agenda Item

38.
Commissioners Court - Regular Session
Meeting Date:
11/19/2024
Title:
Final plat for the Rancho Del Cielo Phase 4 subdivision – Pct 4
Submitted For:
Adam Boatright
Submitted By:
Adam Boatright, Infrastructure
Department:
Infrastructure
Agenda Category:
Consent

Information

Agenda Item

Discuss, consider and take appropriate action on approval of the final plat for the Rancho Del Cielo Phase 4 subdivision – Precinct 4.

Background

This is the next phase of the Rancho Del Cielo development. It consists of 210 single family lots, 2 landscape lots, and 5,305 feet of new public roads. Roadway and drainage construction are not yet complete but a financial security in the amount of $1,774,747.60 has been posted with the County to cover the cost of the remaining construction.  Pursuant to the Commissioners Court action taken September 10, 2019, the County Engineer has approved this final plat in order to meet the review timelines set forth in House Bill 3167.

Timeline
2024-04-23 – initial submittal of the final plat
2024-05-22 – 1st review complete with comments
2024-07-26 – 2nd submittal of final plat
2024-08-07 – 2nd review complete with comments
2024-09-17 – receipt of financial security for remaining construction 
2024-10-30 – 3rd submittal of final plat with signatures
2024-11-06 – 3rd review complete with comments clear
2024-11-14 – County Engineer approval letter sent
2024-11-14 – final plat placed on the November 19, 2024 Commissioners Court agenda for consideration

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 11/14/2024 12:39 PM
Form Started By:
Adam Boatright
Started On:
11/14/2024 08:53 AM
Final Approval Date:
11/14/2024