Commissioners Court - Regular Session
- Meeting Date:
- 11/26/2024
- Title:
- Alpha 24IFB55 CO1 Cul-de-Sac & Straight Section Fog Seal Spring 2024
- Submitted For:
- Robert Daigh
- Submitted By:
- Vicky Edwards, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No 1 to contract number 24IFB55 for Alpha Paving Industries LLC in the amount of $11,364.55 for Cul-de-Sac and Straight Section Fog Seal Spring 2024. Funding Source: 01.0200.0210.003599.
Background
This change order is a balancing change order. All work has been completed. The original contract amount was $347,346.25. With the addition of this Change Order in the amount of $11,364.55, the final contract amount will be $358,710.80. This change order increases the original contract by 3.3%.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 11/21/2024 08:50 AM |
- Form Started By:
- Vicky Edwards
- Started On:
- 11/20/2024 03:07 PM
- Final Approval Date:
- 11/21/2024