Discuss, consider, and take appropriate action on Supplement No. 5 to Work Authorization No. 1 to the RM 1431 (US 183A to IH 35) contract executed November 21, 2023, between Williamson County and STV Incorporated as a successor in interest to CP&Y, Inc. dba STV Infrastructure relating to the LTP/Corridor Program.
Background
STV Incorporated as a successor in interest to CP&Y, Inc. dba STV Infrastructure Supplemental No. 5 to Work Authorization No. 1 is for additional engineering services and public involvement coordination in the amount of $43,050.00 from $620,373.23 to $663,423.23 and extends the termination date to February 27, 2026. Project: P631 Fund Source: Road and Bridge
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Delia Colon | 09/16/2025 04:16 PM |
- Form Started By:
- Ragan Riggs
- Started On:
- 09/15/2025 01:38 PM
- Final Approval Date:
- 09/16/2025