19.
Commissioners Court - Regular Session
- Meeting Date:
- 10/25/2016
- Title:
- 1512-043 SW Bypass Driveways Change Order No. 1
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of -$2,355.24 for Southwest Bypass Driveways, a Road Bond Project in Commissioner Pct. 3
Background
This Change Order provides the final balancing for the overrun/underrun of Contract Quantities on the project as a result of addressing field conditions not accounted for in the original plans. Due to quantity differences between field conditions and the plans, the actual embankment placed was 49% more than the bid quantity. Therefore, twenty-one (21) days have been added to the contract time to complete this extra work. Items 260-6002 and 260-6027 relating to Lime Treated Subgrade were not used due to the quality of the embankment material that was delivered to the project.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 10/20/2016 02:20 PM |
- Form Started By:
- dhaggard
- Started On:
- 10/17/2016 01:08 PM
- Final Approval Date:
- 10/20/2016