21.
Commissioners Court - Regular Session
- Meeting Date:
- 03/28/2017
- Title:
- North Campus Facility - Change Order 2
- Submitted By:
- Gina Wrehsnig, Facilities Maintenance
- Department:
- Facilities Management
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No. 2, to the Agreement between Williamson County and J. T. Vaughn Construction, LLC, in the amount of $114,186.00 for Jacking and Boring for Roadway Sleeve in relation to the Williamson County North Campus Project.
Background
A road sleeve was specified as part of the Inner Loop Road Project so the sewer line for the North Campus Facility could pass under the road. The sleeve is not in place and the North Campus Facility is ready to proceed with the sewer line at this time.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 03/23/2017 09:38 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 03/22/2017 03:27 PM
- Final Approval Date:
- 03/23/2017