27.
Commissioners Court - Regular Session
- Meeting Date:
- 08/01/2017
- Title:
- Justice Center CSCD Remodel P312 - Change Order 2
- Submitted By:
- Gina Wrehsnig, Facilities Maintenance
- Department:
- Facilities Management
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on CO #2 to the Agreement Between Williamson County and S&G Contracting, Inc., in the amount of $54,166.81 to be paid from the Owner’s Contingency, for electrical, acoustical, HVAC, fire stopping and removal of a data rack for the Williamson County Justice Center – CSCD Remodel Project.
Background
This change order provides for a new grid ceiling, lighting and related work at the Justice Centers 1st floor shell space adjacent to the newly remodeled (in progress) CSCD space.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 07/26/2017 09:54 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 07/25/2017 09:39 AM
- Final Approval Date:
- 07/26/2017