1604-068 Forest North Phase 1 Change Order No. 5
Submitted By:
Dawn Haggard, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 5 in the amount of $65,103.79 for Forest North Phase 1, a Road Bond Project in Commissioner Pct. 1.

Background

This Change Order revises drainage work in the Braeburn, Stillforest, and Wisterwood Zones.  The cost of the additional work was paid by overrunning existing pay items where possible; or for work not covered by an existing pay item, the cost of the work was tracked by force account (time and materials).

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 09/21/2017 09:39 AM
Form Started By:
dhaggard
Started On:
09/19/2017 05:09 PM
Final Approval Date:
09/21/2017