- North Campus Facility P324 - Change Order 21
- Submitted By:
- Gina Wrehsnig, Infrastructure
- Department:
- Infrastructure
- Division:
- Building Maintenance
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss and take appropriate action on Williamson County North Campus Project, P324, Change Order #21 from Vaughn Construction in the amount of $10,364.00 for utility adjustments due to elevation changes of drainage structures. This change order is being funded out of the Construction Managers Contingency.
Background
Change order for removing, lowering and replacing the existing irrigation mainline, including a new main valve, double-check valve, wires and other components serving the Central Maintenance Facility building due to the depth required by the new drainage ditch being installed for surface water drainage from the North Campus Facility.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 10/05/2017 08:52 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 10/05/2017 07:46 AM
- Final Approval Date:
- 10/05/2017