- Discuss consider and take appropriate action on Change Order No 1 to contract number IFB 1708-183 for Cross Culvert Replacement
- Submitted For:
- Terron Evertson
- Submitted By:
- Kelly Murphy, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No. 1, to contract number IFB 1708-183, in the amount of $45,558.59 for Cross Culvert Replacement.
Background
This Change Order is a balancing Change Order. All work has been completed and punch list items appropriately resolved. Original contract amount was $626,138.00. With the addition of this change order, of $45,558.59, final contract amount will be $671,696.59.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 05/24/2018 12:08 PM |
- Form Started By:
- Kelly Murphy
- Started On:
- 05/24/2018 11:14 AM
- Final Approval Date:
- 05/24/2018