20.
Commissioners Court - Regular Session
- Meeting Date:
- 08/28/2018
- Title:
- Georgetown Annex P325 - Change Order 15
- Submitted By:
- Gina Wrehsnig, Infrastructure
- Department:
- Infrastructure
- Division:
- Building Maintenance
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on the Williamson County Georgetown Annex Project, P325, Change Order # 15 from Chasco Constructors in the amount of $40,182.81 to approve existing contract funding for miscellaneous subcontractor scopes of work that are necessary to complete the project based on the original design intent. This change order is being funded by the Construction Managers Contingency.
Background
Change order for various necessary scopes of work discovered through Request for Information submitted by the contractors and Architectural Supplemental Instructions issued by the Architect for items that were not specified in the original plans and specs.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 08/23/2018 10:26 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 08/23/2018 07:19 AM
- Final Approval Date:
- 08/23/2018