North Campus Facility P324 - Change Order 65
Submitted By:
Gina Wrehsnig, Infrastructure
Department:
Infrastructure
Division:
Building Maintenance
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider and take appropriate action on the Williamson County North Campus Project; Change Order # 65 from Vaughn Construction in the amount of $80,526.00 to approve funding from within the existing contract for general conditions and a fuel station tank liner. This change order is being funded by Buyout Savings.

Background

This change order is to approve the use of funds that are already inside of the GMP contract to fund additional general conditions due to the extended contract schedule to complete the fuel station and to add a tank liner to the DEF tank excavation for environmental protections.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 10/18/2018 11:40 AM
Form Started By:
Gina Wrehsnig
Started On:
10/18/2018 11:38 AM
Final Approval Date:
10/18/2018