- 1706-168 Inner Loop Improvements Change Order No. 4
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action regarding Change Order No. 4 (Chasco Constructors) in the amount of $20,171.94 for Inner Loop Improvements, a Road Bond project in Commissioner Pct. 3.
Background
This Change Order compensates the Contractor for work needed to construct the new roadway with a uniform cross slope and improve the profile of the existing roadway. Change Order No. 2 documented revisions to the level up asphalt quantities and this Change Order No. 4 documents the revisions to the flexible base in the widening. The Constructor surveyed the existing roadway and it was determined that the profile and cross slopes of the existing roadway had deteriorated to a point that it had to be corrected prior to widening. Once the uniform cross slopes and an acceptable profile grade was determined, the Contractor had to re-survey the work and add flexible base to the pavement section. Per the contract terms, the additional costs were determined by tracking the Contractor's time and materials spent on modifications.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 02/28/2019 09:58 AM |
- Form Started By:
- dhaggard
- Started On:
- 02/27/2019 04:52 PM
- Final Approval Date:
- 02/28/2019