26.
Commissioners Court - Regular Session
- Meeting Date:
- 04/09/2019
- Title:
- 1809-259 Lakeline Right Turn Lanes Change Order No. 1
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 (M.A. Smith Contracting) in the amount of $17,000.00 for Lakeline Right Turn Lane, a Road Bond project in Commissioner Pct. 2.
Project: P331 Funding: Road Bond
Project: P331 Funding: Road Bond
Background
This Change Order adds a force account item to the Contract to pay Austin Energy the cost to extend power service to the HEB west driveway. Austin Energy will extend power from the existing transformer west of HEB's west driveway, along Lakeline Blvd to the HEB west driveway. The County's contractor, Smith Contracting, will make the payment to Austin Energy for the work and the County will reimburse Smith Contracting for the cost. A force account was set up to pay the actual cost, plus an allowable 5% mark up for Smith Contracting and for any unforeseen costs that might occur.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 04/04/2019 09:48 AM |
- Form Started By:
- dhaggard
- Started On:
- 04/02/2019 03:00 PM
- Final Approval Date:
- 04/04/2019