18.
Commissioners Court - Regular Session
- Meeting Date:
- 06/25/2019
- Title:
- 1706-168 Inner Loop Improvements Change Order No. 5
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 5 (Chasco Constructors) in the amount of -$343,688.29, a Road Bond project in Commissioner's Pct. 3.
Project: P226 and P251 Funding Source: Road Bond
Project: P226 and P251 Funding Source: Road Bond
Background
This Change Order provides the final balancing for the overrun/underrun of Contract quantities on the project as a result of addressing field conditions not accounted for in the original plans and adds eight (8) days to the contract for work added in Change Order #2. The cost of Item 999-WC02 Fiber Relocation was unknown prior to the bid. An estimated cost of $250,000.00 was included in the contract for this item. The Contractor submitted a cost of $71,529.14 for the work which resulted in a savings of $178,470.86 to the contract.
This Change Order results in a decrease of $343,688.29 to the Contract amount, for an adjusted Contract total of 5,256,692.67. The original Contract amount was $5,352,696.00. As a result of this final Change Order, $96,003.33 has been deducted from the Contract, resulting in a 1.79% net decrease in the Contract cost.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 06/20/2019 10:29 AM |
- Form Started By:
- dhaggard
- Started On:
- 06/18/2019 02:27 PM
- Final Approval Date:
- 06/20/2019