34.
Commissioners Court - Regular Session
- Meeting Date:
- 08/13/2019
- Title:
- Jail Renovations P411 - Vaughn Change Order #1
- Submitted For:
- Dale Butler
- Submitted By:
- Gina Wrehsnig, Building Maintenance
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on the Jail Renovations Project, P411, Change Order #1 from JT Vaughn Construction in the amount of $131,180.00 to approve Plumbing, HVAC and Intercom services. This change order is being funded by the Project Contingency.
Background
Change order to approve funding for installation of check valves, replacement of an HVAC fan/coil unit, and intercom work in the North and South towers. The original contract included intercom material and equipment only. Due to the timing of adding the north intercom replacement, it was understood that the installation cost would be a change order once the design team and contractor clarified the scope and means of installation.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 08/08/2019 12:00 PM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 08/08/2019 10:38 AM
- Final Approval Date:
- 08/08/2019