Title:
1809-259 Lakeline Right Turn Lanes Change Order No. 3
Submitted By:
Dawn Haggard, Road Bond
Department:
Road Bond
Agenda Category:
Consent

Information

Agenda Item

Discuss, consider and take appropriate action regarding Change Order No. 3 (M.A. Smith Contracting) in the amount of $1,558.22 for Lakeline Right Turn Lanes, a Road Bond project in Commissioner Pct. 2.
P: 331   Funding: Road Bond

Background

This Change Order revises items at the request of Austin Energy (A/E). The conduit layout on the project was revised, which included the relocation of the electrical service pole and foundation away from the proposed sidewalk. A/E also requested revisions to the call-outs on the ground boxes for identification purposes and reduced the wiring for illumination poles. This Change Order also adds a pay item to widen the 6 foot sidewalk to 8 feet, eliminating the need for a bike lane in the existing vehicle travel lane. The sidewalk was previously constructed to a width of 6 feet, due to the proximity to the existing Austin Energy poles. The adjacent rain garden erosion control device was adjusted to provide space for the additional 2 feet required for the sidewalk.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 09/05/2019 10:02 AM
Form Started By:
dhaggard
Started On:
08/28/2019 01:37 PM
Final Approval Date:
09/05/2019