36.
Commissioners Court - Regular Session
- Meeting Date:
- 10/15/2019
- Title:
- Discuss consider and take appropriate action on approval of the final plat for Siena Section 31 subdivision – Pct 4
- Submitted For:
- Terron Evertson
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Division:
- Road & Bridge
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the final plat for Siena Section 31 subdivision – Precinct 4.
Background
This is the next section of the Siena development. This subdivision consists of 177 single family lots and 6,402 linear feet of new public roads. Roadway and drainage construction has been completed.
Timeline
2018-05-31 – initial submittal of the final plat
2018-08-02 – 1st review complete with comments
2018-10-11 – 2nd submittal of final plat
2018-12-18 – 2nd review complete with comments
2019-01-22 – 3rd submittal of the final plat
2019-02-12 – 3rd review complete with comments clear except for completing construction
2019-09-26 – final plat received with all signatures
2019-10-07 – roadway and drainage construction completed
2019-10-10 – final plat placed on October 15, 2019 Commissioners Court agenda for consideration
Timeline
2018-05-31 – initial submittal of the final plat
2018-08-02 – 1st review complete with comments
2018-10-11 – 2nd submittal of final plat
2018-12-18 – 2nd review complete with comments
2019-01-22 – 3rd submittal of the final plat
2019-02-12 – 3rd review complete with comments clear except for completing construction
2019-09-26 – final plat received with all signatures
2019-10-07 – roadway and drainage construction completed
2019-10-10 – final plat placed on October 15, 2019 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 10/10/2019 11:26 AM |
- Form Started By:
- Adam Boatright
- Started On:
- 10/10/2019 10:54 AM
- Final Approval Date:
- 10/10/2019