99.
Commissioners Court - Regular Session
Meeting Date:
07/21/2020
Title:
1809-261 CR 110 Middle CO No. 3
Submitted By:
Dawn Haggard, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No 3 in the amount of $10,419.60 for the CR 110 Middle (James Construction), a Road Bond project in Commissioner Pct. 4.
P: 261 Funding: Road Bond

Background

This Change Order adds Traffic Control Phase 2 Step 2 to the project. This step consists of shifting traffic from the existing lanes of CR 110 to the new lanes from just south of CR 112 to the north end of the project. The construction of this portion of the project is complete and the shift puts traffic in the final configuration at the intersection of University Boulevard and CR 110 which is a benefit to traffic flow. There were utility delays that impacted the completion of this portion from south of CR 112 to Limmer Loop. This traffic shift will allow the Contractor to begin work in the final phase of construction on the portion of roadway adjacent to the traffic switch earlier.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 07/16/2020 08:48 AM
Form Started By:
dhaggard
Started On:
07/15/2020 05:26 PM
Final Approval Date:
07/16/2020