69.
Commissioners Court - Regular Session
- Meeting Date:
- 09/15/2020
- Title:
- 1803-219 - Southwest Bypass Segment 2 Change Order No 4
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $-316,997.71 for Southwest Bypass Segment 2 (James Construction Group), a Road Bond project in Commissioner Pct. 3.
P: 243 Funding: Road Bond
P: 243 Funding: Road Bond
Background
This Change Order provides the final balancing for the overrun/underrun of Contract quantities on the project as a result of addressing field conditions not accounted for in the original plans. A new item was necessary to provide power to the bridge illumination, because the existing service was not in an accessible location.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 09/10/2020 10:44 AM |
- Form Started By:
- dhaggard
- Started On:
- 09/02/2020 02:11 PM
- Final Approval Date:
- 09/10/2020