- 1812-282 Seward Junction Improvements Change Order No. 7
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order #7 in the amount of $194,882.66 for Seward Junction (Jordan Foster Construction), a Road Bond project in Commissioner Pct. 2. P: 271 Funding Source: Road Bond
Background
This Change Order adds the reconstruction of a 500' portion of CR 260 from SH 29 to Terra del sol Parkway to the Contract, at the request of Williamson County. The request for reconstruction is due to the deteriorating condition of the roadway. The scope of work for the reconstruction of this portion of CR 260 did not match the scope of work for the Seward Junction project, so new bid items and unit costs are being added to pay for this work.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 01/28/2021 10:25 AM |
- Form Started By:
- dhaggard
- Started On:
- 01/27/2021 09:09 AM
- Final Approval Date:
- 01/28/2021