Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $28,476.86 for Corridor H/Sam Bass Interim Signals (Austin Traffic Signal), a LTP Corridor project in Commissioner Pct. 1. P: 462  Funding Source: LTP Corridor

Background

This Change Order adjusts bid quantities and adds new items for revisions to the traffic signal installation at the intersection of Great Oaks Drive and Sam Bass Road. The revisions are included in the attached sheets and explained in the paragraphs below. This Change Order also adds a new item to trim the existing trees at Walsh Ranch Boulevard intersection that are blocking signal heads and traffic detectors.

Revision #1: The timber poles on the south side of the intersection of Sam Bass Road and Great Oaks Drive were changed to steel poles with concrete foundations. This change is because there is not enough right of way on the south side to install guy wire support for timber poles.

Revision #2: RFI#7 Adds pedestrian signal elements to maintain the existing cross-walk at the intersection of Great Oaks Drive and Sam Bass Road for pedestrian safety.

Revision #3: RFI#8 Changes the location of the signal controller and the electric service at Great Oaks Drive intersection to the northeast corner. The plan locations were in front of a house in the southwest corner and had an aesthetic impact on the adjacent property.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 04/01/2021 08:49 AM
Form Started By:
Marie Walters
Started On:
03/31/2021 03:25 PM
Final Approval Date:
04/01/2021