58.
Commissioners Court - Regular Session
- Meeting Date:
- 09/28/2021
- Title:
- 2138 CR 101 Change Order No. 3
- Submitted By:
- Mayra Ramos, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 3 in the amount of $81,281.59 for 2138 CR 101 (James Construction), a Road Bond project in Commissioner Pct. 4. Project: 269 Funding Source: Road Bond.
Background
This Change Order adds various items to the project, including the use of full-depth asphalt at the south tie-in of the project, an added driveway, an added strand of barb wire, and a water gap for the fence at Little Mustang Creek.
Item 341-WC03 Full Depth HMAC was utilized to expedite the work at the south tie-in of the CR 101 project. This area was to be constructed with lime-treated subgrade and flexible base, while maintaining traffic access. Use of full-depth hot mix decreased the time for the work from approximately three (3) weeks to two (2) days and maintained a better driving surface during the work. This item was originally added to the contract via Change Order 1.
Item 530-WC01 Driveway provides an additional driveway at Station 172+00, on the east side of the new CR 101 Roadway. This driveway was agreed upon in the landowner agreement. The Lump Sum payment includes the cost of the pavement section for the driveway, culvert pipe and safety end treatments.
Item 552-6003 Wire Fence (Ty C) is in the original contract and includes cost for installation of a five (5) strand wire fence and cattle guard removal and replacement at a cost of $54.67 per LF for a total cost of $95,617.83. This item is being deleted and replaced with separate items; one for the fencing and an item for the cattle guard work.
Item 552-WC01 Wire Fence (Ty C) (Fence Only) is being added to pay for the unit cost of the wire fence only.
Item 552-WC02 Cattle Guard is being added to pay for the unit cost of the removal and replacement of the cattle guard.
Item 552-WC03 Wire Fence (Ty C) (Added Strand) is being added to pay for the extra strand of wire being placed on the five (5) wire fence to match the existing fence.
Item 552-WC04 Wire Fence (Water Gap) is being added to pay for the removal and replacement of the water gap only.
Item 341-WC03 Full Depth HMAC was utilized to expedite the work at the south tie-in of the CR 101 project. This area was to be constructed with lime-treated subgrade and flexible base, while maintaining traffic access. Use of full-depth hot mix decreased the time for the work from approximately three (3) weeks to two (2) days and maintained a better driving surface during the work. This item was originally added to the contract via Change Order 1.
Item 530-WC01 Driveway provides an additional driveway at Station 172+00, on the east side of the new CR 101 Roadway. This driveway was agreed upon in the landowner agreement. The Lump Sum payment includes the cost of the pavement section for the driveway, culvert pipe and safety end treatments.
Item 552-6003 Wire Fence (Ty C) is in the original contract and includes cost for installation of a five (5) strand wire fence and cattle guard removal and replacement at a cost of $54.67 per LF for a total cost of $95,617.83. This item is being deleted and replaced with separate items; one for the fencing and an item for the cattle guard work.
Item 552-WC01 Wire Fence (Ty C) (Fence Only) is being added to pay for the unit cost of the wire fence only.
Item 552-WC02 Cattle Guard is being added to pay for the unit cost of the removal and replacement of the cattle guard.
Item 552-WC03 Wire Fence (Ty C) (Added Strand) is being added to pay for the extra strand of wire being placed on the five (5) wire fence to match the existing fence.
Item 552-WC04 Wire Fence (Water Gap) is being added to pay for the removal and replacement of the water gap only.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/23/2021 10:55 AM |
- Form Started By:
- mayra.ramos
- Started On:
- 09/17/2021 02:01 PM
- Final Approval Date:
- 09/23/2021