41.
Commissioners Court - Regular Session
- Meeting Date:
- 11/09/2021
- Title:
- T1873 Ronald Reagan at Silver Spur & Sun City Change Order No. 1 (final balancing)
- Submitted By:
- Mayra Ramos, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of -$29,746.06 for T1873 Ronald Reagan at Silver Spur and Sun City (QA Construction Services, Inc.), a Road Bond Project in Commissioner Pct.3 P:354 and 357 Funding Source: Road Bond.
Background
This Change Order provides the final balancing for the overrun/underrun of Contract quantities on the project as a result of addressing field conditions not accounted for in the original plans. This Change Order also adds new items to the contract to pay the Contractor for additional work. The added work includes:
999-WC02 Remove and Replace an Existing Flashing Beacon Assembly. The existing flashing beacon was located within the limits of the roadway widening. It was relocated to a location outside the limits of construction.
999-WC03 Milling and Hot Mix for profile revision at Silver Spur. The existing profile of Silver Spur did not match the profile shown in the plans. The proposed profile was modified to match the existing profile and minimize work in the intersection. The modification took place on the departure side of the entrance and the roadway had to be closed to allow the Contractor a safe work zone to complete the work.
999-WC04 Place Block Sod in Center Median of Silver Spur. Trenching for the power service to the new illumination pole and modifications to match the existing profile of Silver Spur disturbed the vegetation in the center median. The existing buffalo grass vegetation was regraded and replaced.
999-WC02 Remove and Replace an Existing Flashing Beacon Assembly. The existing flashing beacon was located within the limits of the roadway widening. It was relocated to a location outside the limits of construction.
999-WC03 Milling and Hot Mix for profile revision at Silver Spur. The existing profile of Silver Spur did not match the profile shown in the plans. The proposed profile was modified to match the existing profile and minimize work in the intersection. The modification took place on the departure side of the entrance and the roadway had to be closed to allow the Contractor a safe work zone to complete the work.
999-WC04 Place Block Sod in Center Median of Silver Spur. Trenching for the power service to the new illumination pole and modifications to match the existing profile of Silver Spur disturbed the vegetation in the center median. The existing buffalo grass vegetation was regraded and replaced.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 11/04/2021 10:00 AM |
- Form Started By:
- mayra.ramos
- Started On:
- 11/02/2021 12:14 PM
- Final Approval Date:
- 11/04/2021