21IFB15 Thrall (S. Bounds Street) - Change Order #1 (Drainage)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $47,437.00 for Project 21IFB15 Thrall (S. Bounds Street) (Chasco Constructors) P:374 Funding Source: Road Bond.

Background

This Change Order revises the location of the drainage pipe and curb inlets to clear existing utilities and changes the curb inlets from precast curb inlets outside the roadway (PCO) to precast curb inlets under the roadway (PCU).  This Change Order also revises the pipe connection between the curb inlet and the pipe under the driveway and increases the quantity of pavement repair due to the current condition of the pavement. 

Following is a summary of the new items required for this Change Order:
ITEM DESCRIPTION QTY UNIT
401-6001 FLOWABLE BACKFILL 150 CY
465-6030 INLET (COMP)(PCU)(3FT)(LEFT) 3 EA
3076-WC01 BLADE LAY TY B HMAC OVER PIPE 10 TON

This Change Order results in a net increase of $47,437.00 to the Contract amount, for an adjusted Contract total of $937,425.00. The original Contract amount was $889,988.00. As a result of this and all Change Orders to-date, the Contract has been increased by $47,437.00, resulting in an 5.3% net increase in the Contract cost. No additional days will be added to the Contract, as a result of this Change Order.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 02/10/2022 08:37 AM