40.
Commissioners Court - Regular Session
- Meeting Date:
- 03/08/2022
- Title:
- Reagan Corridor Segment A LJA Contract Amendment No. 1
- Submitted By:
- Marie Walters, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on a Contract Amendment No. 1 to the Ronald Reagan Corridor Segment A project contract between Williamson County and LJA Engineering, Inc. relating to the LTP Corridor Program. Project: P385. Fund Source: Corridor.
Background
LJA Contract Amendment No. 1 increases the contract compensation cap by $500,000.00 from $500,000.00 to $1,000,000.00. The increase will allow for the execution of Supplemental #1 to Work Authorization #2 in the amount of $485,981.50 to extend the limits of the project by 4.03 miles from RM 2243 to RM 1431 (full project limits are now RM 1431 to SH 29). No other changes are proposed at this time.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 03/03/2022 11:12 AM |
- Form Started By:
- Marie Walters
- Started On:
- 03/02/2022 01:39 PM
- Final Approval Date:
- 03/03/2022