39.
Commissioners Court - Regular Session
- Meeting Date:
- 05/03/2022
- Title:
- 1809-261 CR 110 Middle - Change Order #10 (Final Balancing)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 10 in the amount of ($50.90) for Project 1809-261 CR 110 Middle Section (James Construction Group) P: 261 Funding Source: Road Bond.
Background
This Change Order provides the final balancing for the overrun/underrun of Contract quantities on the project as a result of addressing field conditions not accounted for in the original plans. This Change Order corrects quantities previously reported in Change Order 9.
This Change Order results in a decrease of $50.90 to the Contract amount, for an adjusted Contract total of $8,559,630.60. The original Contract amount was $8,910,862.73. As a result of this and all Change Orders to-date, $351,232.13 has been deducted from the Contract, resulting in an 3.94% net decrease in the Contract cost. Zero (0) additional days will be added to the Contract as a result of this Change Order.
This Change Order results in a decrease of $50.90 to the Contract amount, for an adjusted Contract total of $8,559,630.60. The original Contract amount was $8,910,862.73. As a result of this and all Change Orders to-date, $351,232.13 has been deducted from the Contract, resulting in an 3.94% net decrease in the Contract cost. Zero (0) additional days will be added to the Contract as a result of this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 04/28/2022 08:42 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 04/26/2022 12:10 PM
- Final Approval Date:
- 04/28/2022