Commissioners Court - Regular Session
- Meeting Date:
- 08/09/2022
- Title:
- Historic Courthouse Doors – Vaughn Change Order 3 (4509)
- Submitted For:
- Dale Butler
- Submitted By:
- Wendy Danzoy, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on accepting a report from Vaughn Construction, Change Order No. 3 for the Williamson County Historic Courthouse Doors project. This is a no-cost change order to extend substantial completion to September 30, 2022. Funding Source is 100.1000.4509
Background
This change order is to add 51 days to substantial completion for the Historic Courthouse Doors project (4510). Department point of contact is Dwayne Gossett. On March 6, 2018, the Williamson County Commissioners Court approved Williamson County Facilities Director, Dale Butler, with authority to approve change orders under Local Government Code Sec. 262.031, in relation to Williamson County construction and facilities projects. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Hal Hawes | Hal Hawes | 08/01/2022 10:02 AM |
| County Judge Exec Asst. | Becky Pruitt | 08/01/2022 10:53 AM |
- Form Started By:
- wendy.danzoy
- Started On:
- 08/01/2022 09:48 AM
- Final Approval Date:
- 08/01/2022