Discuss, consider and take appropriate action on a Contract Amendment No. 2 to the Ronald Reagan Widening project contract between Williamson County and CP&Y, Inc. relating to the 2019 Road Bond Program. Project: P336 Fund Source: Road Bonds
Background
CP&Y Contract Amendment No. 2 increases the contract compensation cap by $300,000.00 from $3,000,000.00 to $3,300,000.00. The increase will allow for the execution of a future Supplemental Work Authorization to address safety improvement design at the intersection of Ronald Reagan and Elizabeth Parkway, schematic updates due to Corridor I1 revisions, and additional design and coordination for drainage structures, and a new Work Authorization for construction phase services. No other changes are proposed at this time.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/29/2022 11:11 AM |
- Form Started By:
- Marie Walters
- Started On:
- 09/28/2022 05:45 PM
- Final Approval Date:
- 09/29/2022