Discuss, consider and take appropriate action on accepting a report from Vaughn Construction Co, Change Order No. 4 for the Williamson County Historic Courthouse Doors project. This is a no-cost change order to extend substantial completion to December 16, 2022. Funding Source is 100.1000.4509
Background
This change order is to add 47 days to substantial completion for the Historic Courthouse Doors project. Department point of contact is Dwayne Gossett. On March 22, 2022, the Williamson County Commissioners Court approved Williamson County Architect, Trenton Jacobs, with authority to approve change orders under Local Government Code Sec. 262.031, in relation to Williamson County construction and facilities projects. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court. Funding for this project will be 100.1000.4510.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Hal Hawes | Hal Hawes | 10/11/2022 08:46 AM |
| County Judge Exec Asst. | Becky Pruitt | 10/11/2022 11:29 AM |
- Form Started By:
- wendy.danzoy
- Started On:
- 10/10/2022 02:27 PM
- Final Approval Date:
- 10/11/2022