32.
Commissioners Court - Regular Session
- Meeting Date:
- 11/22/2022
- Title:
- 22IFB39 - CR 111 Westinghouse Rd Change Order #5 (Gateway School Widening)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 5 in the amount of $41,134.66 for Project 22IFB39 CR 111 Westinghouse Rd. (Capital Excavation) P292 Funding Source: Road Bond.
Background
This Change Order compensates the contractor for additional work performed to utilize the existing roadway in front of the Gateway School. To utilize the existing pavement section and build according to the plan width and alignment, the existing curb and sidewalk had to be removed and replaced in front of the school. The items within this area (Stations 77+00 to 86+25) have been adjusted in this Change Order to reflect the changes that have been made to the roadway section.
This Change Order also adds a pay item for flowable fill that is called out in the General Notes, but was not included in the bid tab. Concrete rip rap dissipaters at the culvert outfalls are also being added.
The following new items will be added by this Change Order.
This Change Order results in a net increase of $41,134.66 to the Contract amount, for an adjusted Contract total of $21,780,959.98. The original Contract amount was $21,024,332.88. As a result of this and all Change Orders to-date, $756,627.10 has been added to the Contract, resulting in a 3.60% net increase in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.
This Change Order also adds a pay item for flowable fill that is called out in the General Notes, but was not included in the bid tab. Concrete rip rap dissipaters at the culvert outfalls are also being added.
The following new items will be added by this Change Order.
| ITEM | DESCRIPTION | QTY | UNIT |
| 104-6022 | REMOVE CURB & GUTTER | 874 | LF |
| 104-6015 | REMOVE SIDEWALK | 316 | SY |
| 354-6166 | PLAN ASPH CONC PAV (2-5”) | 2472 | SY |
| 401-6001 | FLOWABLE FILL | 148 | CY |
| 432-6042 | RIP RAP (CONC) (DISSIPATER) | 5.5 | CY |
| 3076-WC01 | TY-B BLADE LAID HMA | 228 | TON |
| 999-WC03 | PAVING MOB | 1 | LS |
| 999-WC04 | SURVEY | 1 | LS |
This Change Order results in a net increase of $41,134.66 to the Contract amount, for an adjusted Contract total of $21,780,959.98. The original Contract amount was $21,024,332.88. As a result of this and all Change Orders to-date, $756,627.10 has been added to the Contract, resulting in a 3.60% net increase in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 11/17/2022 10:48 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 10/26/2022 07:15 AM
- Final Approval Date:
- 11/17/2022