51.
Commissioners Court - Regular Session
Meeting Date:
12/06/2022
Title:
T5045 - CR 404 Hutto Water Line Realignment Change Order #4 (UPRR Monitor Flagging)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $89,204.91 for Project T5045 CR 404 Hutto Water Line Realignment (Austin Underground, Inc.) P 390 Funding Source: Road Bond.

Background

This Change Order adds an item for track monitoring and flagging operations at the Union Pacific Railroad (UPRR) at CR 401 and CR 402. Track monitoring and flagging are required by Union Pacific and must be provided by the Contractor performing the work on or near the railroad easement.

A new UPRR Monitoring and Flagging bid item will be added to the Contract to allow for payment.

This Change Order results in a net increase of $89,204.91 to the Contract amount, for an adjusted Contract total of $3,427,311.16. The original Contract amount was $2,897,639.00. As a result of this and all Change Orders to-date, $529,672.16 has been added to the Contract, resulting in an 18.28% net increase in the overall Contract cost.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 12/01/2022 10:26 AM
Form Started By:
Julissa Romero
Started On:
11/29/2022 08:43 AM
Final Approval Date:
12/01/2022