- T5045 - CR 404 Hutto Water Line Realignment Change Order #5 (Line Stop & Balancing)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 5 in the amount of ($155,246.74) for Project T5045 Hutto Water Line Realignment (Austin Underground, Inc.) P: 390 Funding Source: Road Bond.
Background
This Change Order provides the final balancing for the overruns/underruns of Contract quantities on the project that are a result of addressing field conditions not accounted for in the original plans. This Change Order also adds line stops, gate valves, and open cutting for encasement to allow for an easier transition from the old water line to the new water line.
This Change Order also adds an additional sixty-six (66) days to the Contract. The additional time was necessary to account for the time it takes to fuse of the HDPE pipe, installing a temporary bypass water line at CR 401, and for the permanent relocation of the Jonah water line on CR 401.
Multiple items will be added by this Change Order. Please see attached Change Order.
This Change Order results in a net decrease of $155,246.74 to the Contract amount, for an adjusted Contract total of $3,272,064.42. The original Contract amount was $2,897,639.00. As a result of this and all Change Orders to-date, $374,425.42 has been added to the Contract, resulting in an 12.92% net increase in the overall Contract cost. As a result of this Change Order, sixty-six (66) days will be added to the contract.
This Change Order also adds an additional sixty-six (66) days to the Contract. The additional time was necessary to account for the time it takes to fuse of the HDPE pipe, installing a temporary bypass water line at CR 401, and for the permanent relocation of the Jonah water line on CR 401.
Multiple items will be added by this Change Order. Please see attached Change Order.
This Change Order results in a net decrease of $155,246.74 to the Contract amount, for an adjusted Contract total of $3,272,064.42. The original Contract amount was $2,897,639.00. As a result of this and all Change Orders to-date, $374,425.42 has been added to the Contract, resulting in an 12.92% net increase in the overall Contract cost. As a result of this Change Order, sixty-six (66) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 12/08/2022 09:40 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 12/07/2022 07:25 AM
- Final Approval Date:
- 12/08/2022